Tips and Traps

Exhibit 7.1 — Sample issues log A

No.

DATE

OPEN ISSUE

RESOLUTION

DATE

21

12 Jul

Budgetary implications of recommendations need to be assessed before Additional Estimates

13 Jul meeting: keep under review

 

28

14 Jul

Consultant requested to attend special meeting with another agency

20 Aug: difficulties in arranging meeting due to interagency policy differences

 

51

15 Oct

Agency asked consultant to confirm specifically that project is on track, and that no extra work was being done that would lead to a claim for additional fees.

15 Oct: on track

23 Dec: reconfirmed

 

Exhibit 7.2 — Sample ‘issues log’ B

No.

DATE

CLOSED ISSUE

RESOLUTION

DATE

1

15 Jan

Consultant requires clarification of process for claiming expenses

15 Jan: agreed that tax invoices to be submitted to Mr Smith

15 Jan

2

23 Jan

Consultant raised problems regarding data base

23 Jan: agreed that Ms Jones will check data

25 Feb: IT section requested to provide software to enable transfer of revised data to consultant

26 Feb: consultant confirms receipt of data

26 Feb

3

12 Feb

etc

etc