Exhibit 7.1 — Sample issues log A
|
No. |
DATE |
OPEN ISSUE |
RESOLUTION |
DATE |
|
21 |
12 Jul |
Budgetary implications of recommendations need to be assessed before Additional Estimates |
13 Jul meeting: keep under review |
|
|
28 |
14 Jul |
Consultant requested to attend special meeting with another agency |
20 Aug: difficulties in arranging meeting due to interagency policy differences |
|
|
51 |
15 Oct |
Agency asked consultant to confirm specifically that project is on track, and that no extra work was being done that would lead to a claim for additional fees. |
15 Oct: on track 23 Dec: reconfirmed |
Exhibit 7.2 — Sample ‘issues log’ B
|
No. |
DATE |
CLOSED ISSUE |
RESOLUTION |
DATE |
|
1 |
15 Jan |
Consultant requires clarification of process for claiming expenses |
15 Jan: agreed that tax invoices to be submitted to Mr Smith |
15 Jan |
|
2 |
23 Jan |
Consultant raised problems regarding data base |
23 Jan: agreed that Ms Jones will check data 25 Feb: IT section requested to provide software to enable transfer of revised data to consultant 26 Feb: consultant confirms receipt of data |
26 Feb |
|
3 |
12 Feb |
etc |
etc |